What it means

What you see. One of:

  • The enrichment date is not today. Nothing was changed.: a date write of Askling last enrichment was refused before anything was sent. The first sentence can also be The enrichment date holds no date., The enrichment date is not a whole day. or This is not Askling's enrichment date on a company.
  • This enrichment date waited too long and was not written. The next run dates the company again.: a date that waited more than two days, for example while Askling was paused, was not written. Nothing failed: the next run writes today's date without asking the AI again.
  • HubSpot has a property askling_last_enrichment that is not a date. Askling never changes its type. Archive it in HubSpot, then try again.: HubSpot already has a property with that name that is not a date, so Askling cannot create its own.
  • Confirm first: Askling creates a date field in HubSpot.: Create in HubSpot for the date field was sent without the confirmation.

Why it happened

The engine writes only today's date, only in askling_last_enrichment, only on a company. A date row that was changed, or is days old, is refused. The conflict means someone made a property with the same internal name but another type. The confirmation error means the request skipped the dialog.

What to do

  1. Open Enrichment and leave a refused or late date write alone. The next run dates the company again.
  2. If HubSpot has a property with that name that is not a date, open HubSpot Settings, then Properties.
  3. Archive that property. HubSpot lets you restore an archived property.
  4. In Askling, open Enrichment, then Configuration, and click Create in HubSpot.
  5. If it asks you to confirm first, click Create the field in the dialog.

Check it worked: the date field exists in HubSpot and the next run dates the company.

See Askling last enrichment and when a company is tried again.